Domestic Terminal Power Interruptions (3, 10, 17 December)
Published on November 28, 2024
As part of the DTB Security Upgrades, Lendlease are required to undertake a number of High Voltage switching operations over the coming 3 weeks. During these periods, stakeholders can expect power interruptions to affect Level 1 and 2 of the Common User Area between Gates 25 and 38 and including the Centre Satellite, tenancies, apron lighting and Aerobridges.
These works are scheduled for:
- 00.45 – 0100 hrs. on 3 December
- 00.45 – 0100 hrs. on 10 December
- 00.45 – 0100 hrs. on 17 December