Domestic Terminal Baggage Makeup Area - Works Update - 21 February 2024
Published on February 21, 2024
The Baggage Security Upgrade Project is currently in progress at the DTB, focusing on baggage handling. The project involves migrating the DTB North (Qantas) High-Level Controls. Programming and factory acceptance activities began in September 2023, followed by onsite deployment and testing that commenced in January 2024. Site acceptance testing is currently in the final stages of completion.