Airport Intake Substation (AIS) Upgrade works
AIS switchboard and comms room works have commenced.
Project location – AIS Switchboard & Comms Room (adjacent to Automall site)
Project start – August 2023 – January 2024
Construction schedule – day works
Project Update
This project will upgrade the HV infrastructure, including the design and construction, of a new communication distribution facility at the Airport Intake Substation (AIS). The proposed expansion of the existing AIS switchboard aims to provide increased capacity to support precinct developments and improve network reliability.
To provide some background, BAC owns and operates a private 11kV distribution network across the 2,700-hectare Brisbane airport site. BAC’s private network is connected to the local power authority otherwise known as a Distribution Network Services Provider (DNSP) via three intake substations namely Airport Intake Substation (AIS), Lomandra Drive Intake (LIS) Substation and Pandanus Avenue Intake Substation (PIS).
Airport Intake Substation is located on the Airport Drive side and supplies power to International Terminal Building (ITB), Qantas Zone Substation (QZS, supporting Export Park, Qantas drive buildings), Central Parking Area (CPA), New Parallel Runway (NPR), the Airport Control Tower and the TAAATS buildings.
There is existing telecommunications infrastructure co-located within the Airport Intake Substation building. The existing AIS telecommunications infrastructure is a major distribution node within the wider airport precinct and presently provides connectivity across both terminals including substations and security (CCTV and access control).
Current project timelines are as follows:
| Contractor | Scope | Timeframe | From Date | To Date |
| Pensar | Construction of New Comms Building | In progress | 4 Oct 2023 | |
| Programmed | Comms room new fit-out and cutovers |
10 weeks
|
5 Oct 2023 | 13 Dec 2023 |
| Pensar | Demolition and make good old comms room wall | 1 week |
14 Dec 2023
|
20 Dec 2023 |
| LAI | Installation, testing and commissioning new HV | 2 weeks | 10 Jan 2024 | 24 Jan 2024 |
The next update for this project will be in September.
Project contacts
A BAC reminder to not engage the project contractor and direct all project enquiries to:
Nik Kahler - Project Manager
Email - [email protected]
Alternatively, please contact the Airport Duty Manager number (contactable 24/7)
(07) 3406 3171