Mon 21 to Thu 24 August - International Terminal Electrical Testing

Published on August 10, 2023

Power interruption times will vary from 30 seconds to a maximum of 5 minutes and will be coordinated to minimise operational impact and will occur daily between 2000 – 0600 as per the dates below.

 

During this period, interruptions will only occur in areas where normal operations are not taking place and will be coordinated between the Airport Duty Managers and attending Electricians.

 

  • L1 All Areas & L1 Apron - Monday 21st August 20:00hrs – Tuesday 22nd August 06:00hrs 
  • L2 All Areas & L1 Apron - Tuesday 22nd August 20:00hrs – Wednesday 23rd August 06:00hrs
  • L3 Landside & L3 Airside - Wednesday 23rd August 20:00hrs – Thursday 24th August 06:00hrs
  • L4 All Areas - Thursday 24th August 20:00hrs – Friday 25th August 06:00hrs

 

This notice is for general information, and we do not anticipate disruptions to any tenancy power supplies, but it is advised that as a precaution, critical data should be backed up prior to the above commencement times.